The remaining sections progress from west to central to east through the
new construction. Within a section, views proceed south to north.
|
Some Details
|
Outside the corridor west of the temporary Science Library, spacers provide
a base for flooring forms. Normally, metal bins are used for this purpose,
but smaller spacers are needed in small areas.
|
|
Inserts provide space for electrical conduit that must go through concrete
beams.
|
A metal bracket is screwed to the wall, near the corridor window
just outside Minna Mahlab's office.
|
|
Another bracket attaches to the existing wall, near the northern window
(near Minna Mahlab's office).
|
|
Western Section
|
Western section: Shoring is being inserted on top of the first floor,
beginning near the northern corridor of the Science building (1951 wing).
|
|
Western section: A second view of the start of shoring activities.
|
|
Central Section
|
Central section: The southern part of the central section provides
storage for supplies, while column forms are being constructed near the
eastern section (in the distance).
|
|
Central section: Concrete is transported by tower crane to fill the column
forms.
|
Central section: A mezzanine in the Science Library is located in the
northern part of the central section. Shoring is being put in place for
this mezzanine (right).
|
|
Central section: Shoring and forms for the mezzanine take shape.
|
|
Eastern Section
|
South Eastern Section: Rebar mats are largely in place for the first
floor deck, just north of the Math/CS/Psych wing of the existing buidling.
|
|
Eastern Section: Moving into the middle part of the eastern section, rebar
is in place for many beams. Rebar flooring mats are prepared up to a
point; thereafter the floor decking is in place, but rebar installation is
incomplete.
|
North Eastern Section: In the northern section, parts of beam rebar have
been installed, but additional rebar is needed for beams, and the flooring
rebar has not been started.
|